{"id":685,"date":"2009-03-24T13:53:32","date_gmt":"2009-03-24T17:53:32","guid":{"rendered":"https:\/\/qa-origin-www.parsons.com\/?post_type=project&p=685"},"modified":"2024-01-31T10:29:46","modified_gmt":"2024-01-31T15:29:46","slug":"salt-waste-processing-facility","status":"publish","type":"project","link":"https:\/\/www.parsons.com\/project\/salt-waste-processing-facility\/","title":{"rendered":"Salt Waste Processing Facility – Phase II – Aiken, SC"},"content":{"rendered":"

Processing Radioactive Waste<\/h3>\n

\"\"<\/p>\n

For more than 25 years, Parsons has supported the U.S. Department of Energy (DOE) at its Savannah River Site (SRS). The site, originally constructed in the 1950s by the Atomic Energy Commission, produced the basic materials required to fabricate nuclear weapons for our nation\u2019s defense programs.<\/p>\n

After the Cold War, the SRS shifted focus to environmental restoration and remediation. In 2004, the DOE selected us to design, build, commission, and operate for one year the Salt Waste Processing Facility (SWPF), which will eventually process 31 million gallons of radioactive salt waste stored onsite in large underground tanks<\/p>\n

Ahead of Schedule, Under Budget<\/h3>\n

We completed construction of SWPF in April 2016, eight months ahead of the target schedule and more than $65 million under the target cost of the contract for construction activities. After construction was complete, we tested the plant\u2019s systems and trained the workforce to operate the plant in preparation for the start of operations in 2018.<\/p>\n

Custom Solutions<\/h3>\n

To obtain the data necessary for the design of this one-of-a-kind facility, our team developed two specific programs:<\/p>\n